A Biomass EfW facility Thetford Power Station runs primarily on Poultry Litter, MBM and Virgin Wood this 38.5MW plant has been operated by MRE/EPR Thetford Ltd since 1999.[1]


Thetford Power Station
Operational
Site Location
Site Location

See Biomass EfW → page for a larger UK Wide map.

Operator Melton Renewable Energy Ltd (MRE)
Capacity 44.2 MWe
Feedstock Virgin/Poultry Litter
EPR (Waste Licence) PP3235LP
ROC Yes
CfD
CHP Unkwn

Operators Annual Report


Input Data

Year Wood Litter RDF Other Total
2018 38274 422583 0 0 460857
2019 43461 449655 0 0 493116
2020 59713 431356 0 5922 496992
2021 51881 390383 0 55589 497853
2022 62297 337561 0 61623 461481


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2018 8782 1.91% 1337 0.29%
2019 7994 1.62% 686 0.14%
2020 7995 1.61% 686 0.14%
2021 10951 2.20% 13339 2.68%

Thetford Power Station - geograph.org.uk - 422118
Thetford Power Station - geograph.org.uk - 422118


Summary

A Biomass EfW facility Thetford Power Station runs primarily on Poultry Litter, MBM and Virgin Wood this 38.5MW plant has been operated by MRE/EPR Thetford Ltd since 1999.

Plant

The plant's first power was generated in June 1999, with Taylor Woodrow Management and Engineering carrying out the design and construction turnkey package at a cost of £69m. The Fuel handling was by Birtley Engineering plc, the roto grate[2] (Grate) by Detroit Stoker Inc., the boiler by Foster Wheeler Ltd (Canada) and the turbine by Ansaldo Energia SpA[3]

Annual Sustainability Tonnage Input/Fuel

The tonnage[4] received by the plant in the most recent Annual Sustainability Report and for the previous 3 years for 2020/21 was reported by Ofgem as below[5]:

Year Waste Wood (m3) Waste Wood (t) Straw Miscanthus Arboricultrual Waste Sawmill Residue Foresrty Residue Round Wood Short Rotation Coppice MBM Other Material
2020/21 0 0 0 0 35940 0 21568 0 0 5921 428699
2019/20 0 0 0 0 31857 0 18211 0 0 0 459437
2018/19 0 0 0 0 25965 0 11076 0 0 0 413527
2017/18 0 0 0 0 0 0 0 0 0 0 0

Waste Tonnage, By Origin

The table shows a list of the Waste for the Permit PP3235LP, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data was last updated on October 2023. The total reported tonnage arriving at the site was: 212,010.68t. Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:

  • Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
  • Material may have been received into the site but treated in some other way than incineration.
  • Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code Origin of Waste Tonnes In
02 02 02 Suffolk 4757.02
02 01 99 Norfolk 11493.16
02 01 07 Norfolk 28745.94
02 01 99 Suffolk 13176.14
02 02 02 Norfolk 2555.52
02 01 06 Norfolk 151282.90


References

  1. https://www.mreuk.com/thetford
  2. Annual Report 2021
  3. http://www.engineering-timelines.com/scripts/engineeringItem.asp?id=992
  4. In the case of EfW plants with gasification technology the figures are reported in terms of cubic metres of syngas produced rather than tonnes used
  5. Biomass Sustainability Dataset 2020-21