Widermerpool Biomass Power Plant

From WikiWaste

A Biomass EfW facility Widermerpool Biomass Power Plant (also known as Sherwood Biomass Facility) is designed to operate primarily on Wood Waste generating 6.7MWe (5.7MWe to the grid) and 4.5 MWth heat for the adjacent sawmill operation[1].


Widermerpool Biomass Power Plant
Operational
Site Location
Site Location

See Biomass EfW → page for a larger UK Wide map.

Operator Equitix ESI CHP (Nottingham) Ltd
Capacity 6.7 MWe
Feedstock Waste Wood
EPR (Waste Licence) QP3936AX
ROC Yes
CfD
CHP Yes

Operators Annual Report


Input Data

Year Wood Litter RDF Other Total
2018 25107 0 0 0 25107
2019 48730 0 0 0 48730
2020 53373 0 0 0 53373
2021 49199 0 0 0 49199
2022 49135 0 0 0 49135


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2018 855 3.41% 269 1.07%
2019 1497 3.07% 468 0.96%
2020 2131 3.99% 617 1.16%
2021 1774 3.60% 662 1.34%
2022 2146 4.37% 600 1.22%

Thetford Power Station - all rights reserved Alpha Construction
Thetford Power Station - all rights reserved Alpha Construction


Summary

A Biomass EfW facility Widermerpool Biomass Power Plant is designed to operate primarily on Wood Waste generating 6.7MWe and heat for the adjacent sawmill operation (John Brook Sawmill, Waring Waste). Owned by Equitix it is operated under a 20 year contract for them by Veolia which commenced in 2015[2].

Plant

Developed by Pinnacle Power and Mycock Associates the plant was built by STC Power for Equitix and is operated by Veolia. Alpha Construction Ltd acted in the role of Principle Contractor for STC Power under CDM, with delivery of the concrete foundation/pit strucutre, foundations, floors etc[3] the total plant is reported to have cost £30m[4] and is based on mving [[grate technology[5].

Annual Sustainability Tonnage Input/Fuel

The tonnage[6] received by the plant in the most recent Annual Sustainability Report and for the previous 3 years for 2020/21 was reported by Ofgem as below[7]:

Year Waste Wood (m3) Waste Wood (t) Straw Miscanthus Arboricultrual Waste Sawmill Residue Foresrty Residue Round Wood Short Rotation Coppice MBM Other Material
2020/21 0 40207 0 0 0 0 0 0 0 0 0
2019/20 0 45708 0 0 0 0 0 0 0 0 0
2018/19 0 29017 0 0 0 0 0 0 0 0 0
2017/18 0 0 0 0 0 0 0 0 0 0 0

Waste Tonnage, By Origin

The table shows a list of the Waste for the Permit QP3936AX, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data was last updated on October 2023. The total reported tonnage arriving at the site was: 49,134.64t. Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:

  • Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
  • Material may have been received into the site but treated in some other way than incineration.
  • Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code Origin of Waste Tonnes In
19 12 07 Nottinghamshire 44410.72
19 12 07 Rotherham 877.22
19 12 07 Sheffield 2817.06
19 12 07 Manchester 690.56
19 12 07 East Riding of Yorkshire 339.08


References